With "Three certificates" issued in five days, the commencement of construction of the power grid project has entered the countdown

Release date:2022-01-24    
  • |
  • |
  •   Recently, the reporter learned from State Grid Dongli Branch that the preliminary work of the 110 kV line project from Yangbei Road to Yaoliu Bridge has made significant progress. The project has set a record of obtaining three approval documents for "project approval, written opinion on site selection and line selection, and project planning permit" at one time, marking that the construction of the project has been fully guaranteed according to law and the commencement of construction has entered the countdown.

      "Once again, we deeply feel that the government departments of the free trade zone should the responsibility to take the initiative to serve enterprises and assist in the construction of the project," said State Grid Dongli Branch. The Planning and Construction Bureau took the initiative to provide services in routing and design program review in the early stage of the project, and helped coordinate with relevant departments to implement the specific line location of the pipeline. With the strong support of various departments in the free trade zone, it only took 5 days to complete the procedures from filing an application to obtaining all approval documents of the project, realizing the "simultaneous issuance of three certificates" of the core preliminary essential documents of linear power grid project for the first time.


    checktaskdate=&unchecktaskdate=&titleformatstring=False_False_False_&oldnodeid=&oldnewid=&oldcontentid=&Check_IsAdmin=True&Check_UserName=bsqgwh_check&Check_CheckDate=2022/1/24 18:19:49&Check_Reasons=

    All Copyright Reserved by Tianjin Port Free Trade Zone Administrative Committee

    Administration Building No.166,Xi San Dao,Tianjin Port Free Trade Zone Administrative Committee,Tianjin,china 300308

    E-mail:tjftz@adm.tjftz.gov.cn